Cemher Microne. Calculated for 40 m² of floor with Medio as the finish.
128 kg of microcement. Waiting time from 39.5 to 53 hours.
to get the quantity per layer and the schedule for the job. The figures are from Cemher's technical data sheet.
See the build-up step by stepTiles add joint filler to the schedule.
Quantity
128 kg of microcement for 40 m².
Waiting time from 39.5 to 53 hours.
| Layer | Product and basis | Buckets | Quantity |
|---|---|---|---|
| Primer | Primer 100One coat, 6 to 8 m² per litre | from 5.0 to 6.7 litres | |
| Base coat | Microne Plus BaseTwo coats, 1 kg per m² per coat | 8 buckets of 10 kg | 80 kg |
| Finish | Microne Plus MedioTwo coats, 0.6 kg per m² per coat | 5 buckets of 10 kg | 48 kg |
| Hardener | Microne Plus hardenerFor all four coats | Ask Zenzorama about the quantity. | |
| Varnish | Aquamax ProTwo coats, three in wet rooms and areas with heavy traffic | Ask Zenzorama about the quantity. | |
Schedule.
Total waiting time: from 39.5 to 53 hours. Working time comes on top.
- Primer 1000.5 to 2 hours
- Base, first coat4 to 8 hours
- Base, second coat4 to 8 hours
- Finish, first coat4 to 8 hours
- Finish, second coat24 hours from the last coat to varnish24 hours
- Varnish, first coat3 hours
- Varnish, second coatWater and full use after 5 daysFinal step
Total39.5 to 53 hours
Dark line: shortest waiting time. Light line: longest.
Source: Cemher's technical data sheets for Microne and Primer 100.
Zenzorama, phone 400 08 038. The calculation is on zenzorama.no